Machinery Relocation in ICAD: Planning a Factory Move

The Industrial City of Abu Dhabi, ICAD, is a large manufacturing area in Mussafah made up of ICAD I, II and III. Factories here make building materials, process food, fabricate steel and run many other production lines. When a machine has to be installed, replaced or moved, the work competes directly with production: every hour the line is stopped has a cost. This guide walks through how to plan a machinery move so it fits inside the downtime you can afford.
Step 1: Describe the Machine Properly
A supplier can only plan the move from accurate information. Collect:
- Weight. Use the manufacturer's data plate or manual, not an estimate. Note whether the figure includes oil, tooling or attachments.
- Dimensions, including the tallest and widest points.
- Centre of gravity. Many machines are much heavier at one end. If the manual shows it, share it.
- Lifting points. Find out whether the machine has lifting eyes, forklift pockets or a base frame that can take skates or jacks.
- Photos from all four sides and from above if possible.
A machine that looks symmetrical and is not is the most common cause of a relocation going wrong.
Step 2: Survey the Route Inside the Building
The path from where the machine sits to where it is going matters as much as the lift. Walk it and check:
- Floor loading. The combined weight of the machine and the forklift is concentrated on a few wheels. Suspended floors, trench covers and thin slabs may need steel plates or a different route.
- Headroom. Measure under beams, ducts, cable trays, sprinkler pipes and door lintels.
- Width and turning space, especially at doorways and between running lines.
- Obstacles that can be removed for the move, such as guardrails or a section of racking.
Share the measurements, or ask for a site visit. The route often decides the method.
Step 3: Choose Forklift, Crane or Both
- A heavy forklift suits machines that can be picked up from below and carried across a level floor. Our forklifts run up to 25 tonnes.
- A mobile crane is needed when the machine must be lifted over something, lowered through a roof opening, or loaded onto a trailer from above. For lifts inside a building, headroom limits how far the boom can be raised, so the crane size has to be chosen with the roof height in mind.
- A telehandler helps where a load must be placed at reach, such as onto a mezzanine.
- A combination is common: a forklift brings the machine to the door and a crane loads it.
Our guide to choosing the right crane capacity explains why radius and height matter more than the headline tonnage, and the forklift versus telehandler comparison covers the difference between those two machines.
Step 4: Fit the Work Into the Shutdown
Plan backwards from the moment production has to restart.
- Before the shutdown: confirm the method, the equipment and the route. Have the new foundation, anchor bolts and services ready.
- Disconnection: power, air, water, hydraulics and extraction are isolated and disconnected by your maintenance team or the machine supplier.
- The move: the lift and transport itself is often the shortest part.
- Positioning and levelling at the new location.
- Reconnection and commissioning.
The lift is rarely what overruns. Delays usually come from a foundation that is not ready, an obstruction nobody measured, or a document the site safety team needed. Our pre-lift safety checklist lists the checks to complete beforehand.
Step 5: Moving Between Sectors or Sites
If the machine is leaving the building, it travels on a flatbed or lowbed trailer. Tell your supplier the loaded height and width, because a tall machine on a trailer can exceed normal road limits and need route approval first. Our article on oversized-load permits explains when that applies, and the lowbed delivery checklist covers preparing the receiving site.
Why Being Close to ICAD Helps
ICAD is next to Mussafah, where our yard is, so standard equipment typically arrives within a short window: around 60 to 90 minutes for a forklift, and the same day for a mobile crane on a standard machinery lift. For a factory, that matters in two situations: an unplanned breakdown where a failed machine has to be pulled out quickly, and a planned shutdown where a second machine is suddenly needed to stay on schedule.
Machinery Relocation in ICAD With Maxtgc
Maxtgc supplies forklifts, mobile cranes, telehandlers and trailers for machinery moves and shutdown work across ICAD I, II and III, with certified operators and dispatch running 24/7. See our ICAD coverage, the forklift rental and mobile crane rental pages, or request a quote with your machine's weight and photos.